This project has been constructed and is in service.

Excavation for Phase 1 of the deep soil mixing ground improvement for the  I-10: Ft. Grant TI project. NCS was subcontracted by Speedie and Associates, Inc. to provide recommendations for the design of ground improvement under the center piers of a new bridge at the Fort Grant Road Traffic Interchange (TI) in Wilcox, AZ.

The Wilcox area has a complex geology, including Playa landforms with salt flats at the surface, and soft clay layers at depth. One or more of the clay layers appears to be underconsolidated. Drilled shaft and spread footings were found to have unacceptable settlements at the pier location of the new bridge, and NCS was tasked with providing ground improvement recommendations.

Rig used for deep soil mixing on the I-10: Ft. Grant TI project. Deep soil mixing (DSM) was selected as the method of ground improvement, with spread footings to be constructed over the improved subgrade. In late winter to early spring of 2006, Hayward Baker Inc. performed Phase 1 of the DSM. The first half of the new bridge was constructed and brought into service, and the remainder of the old bridge was demolished. In late summer to early fall of 2006, Phase 2 of the DSM was performed and completed.

This proeject has been constructed and is in service.

Deep Soil Mixing ground improvement to mitigate unacceptable anticipated settlements

Innovative anlaysis and design to prevent stress transfer to softer clay layers at depth

Photos
Bearing capacity analysis for the I-10: Ft. Grant TI. Excavation for Phase 1 of the deep soil mixing ground improvement for the  I-10: Ft. Grant TI project. Deep soil mixing paddles used for ground improvement on the I-10: Ft. Grant TI project. Sampler used to obtain samples from the soil-cement column. Used on the I-10: Ft. Grant TI project. Sampler used to obtain samples from the soil-cement column attached to the paddles. Used on the I-10: Ft. Grant TI project. Grout plant used on the I-10: Ft. Grant TI project. Deep soil mixing rig used on the I-10: Ft. Grant TI project. Drilling and mixing a column on the deep soil mixing ground improvement of the I-10: Ft. Grant TI project. Grout plant used for deep soil mixing on the I-10: Ft. Grant TI project. Testing the grout nozzles on the paddles before mixing a new column on the deep soil mixing performed for the I-10: Ft. Grant TI project. Testing the grout nozzles on the paddles before mixing a new column on the deep soil mixing performed for the I-10: Ft. Grant TI project. Exposed soil-grout columns created by deep soil mixing on the I-10: Ft. Grant TI project. Photo courtesy of Gary Taylor of Hayward Baker, Inc. Exposed soil-grout columns created by deep soil mixing on the I-10: Ft. Grant TI project. Photo courtesy of Gary Taylor of Hayward Baker, Inc. Exposed soil-grout columns created by deep soil mixing on the I-10: Ft. Grant TI project. Photo courtesy of Gary Taylor of Hayward Baker, Inc. Exposed soil-grout columns created by deep soil mixing on the I-10: Ft. Grant TI project. Photo courtesy of Gary Taylor of Hayward Baker, Inc.
 
 

Page Last Updated on 05/15/08 09:36 am MST (-07:00)